带有期限值的作业调度问题,已知n=4,(p1,p4,p3,p2)=(100,20,15,10)和(d1,d4,d3,d2)=(2,1,2,1)。使用FJS算法,数组F(0,2)的初值分别是( )\n \n \n \n \n \n \n

\n \n \n \n A.\n 0,0,0\n

\n \n

\n \n \n \n B.\n 0,1,2\n

\n \n

\n \n \n \n C.\n -1,-1,-1 \n